Municipality of Haarlemmermeer
The municipality of Haarlemmermeer is in a period of change. In preparation for the move to the new Hoofddorp based Town Hall in 2027, the municipality are using a new temporary space designed by Hollandse Nieuwe to already transition from a traditional office space, with a focus on individual workspaces, towards a new hybrid work environment with a wide variety of shared workplace options.
Sustainability, health, and circularity are considered important pillars of the new workplace strategy and of the new ”temporary” location.
| client | Municipality of Haarlemmermeer |
| program | Council chamber, offices, meeting centre |
| completion | 2022 |
| area | 9500 m² |
| location | Hoofdorp |
| sustainability | Carbon footprint 49.738 tonnes |


A sustainable success story
in a circular building
The new accommodation consists of two towers connected by a single-storey level on the ground floor. The building provides an open, shared working environment without any rooms designated to a single user. Each department will have a home-base area where direct colleagues can find each other and access different styles of workspaces that support their different needs.
By creating enough concentration, workstations, team spaces and various sizes of meeting rooms in each open-plan area, employees can easily find the most suitable place for their specific activities.




The existing identity and colours of the municipality of Haarlemmermeer have been used extensively throughout the new space. Fragments of the illustrative logo have been selectively on walls and doors along with accents of the logos colours, giving the work environment the look and feel of the municipality as well as helping create a clear navigation and zoning.



Circularity, health, and sustainability
Sustainability and reuse are hugely important principles in this project. For example, the existing ceilings have been retained and 100% of the walls, doors, furniture, and other elements that were part of the previous occupant’s interior were reused and integrated into the municipalities new space. Where possible, existing wall positions were retained to minimise investment in new acoustic elements.
In several cases, re-usable products were resourced from other locations or projects. Aluminium framed glass doors from a separate project were dismantled and rebuilt in Hoofddorp for the temporary space, the old council chamber was completely dismantled, modified, and rebuilt in the new location and moss panels that were previously scattered throughout the old town hall were collected and placed on the walls in the council chamber, contributing significantly to the acoustics and experience of this important space.


The new public counter, reception desk, cabinetry and the pantries are made of clear FSC-certified birch plywood coupled with sheets of recycled plastic. Efforts were made to design from standard sheet sizes to minimise sawing losses and all these products are demountable and thus easily reusable in their continued, long-life cycle.


Partners
This project was partly realized by many participating design partners and parties, with whom which we have greatly enjoyed working together with. Our thanks goes out to:
Building specialist: Verwol
Project management: Con2epts
Installation advisor: J. van Toorenburg BV